Slabs, footings, post holes and steps: the cubic metres, the bags and the mix.

What are you pouring?
Units
m
m
mm

100 mm for most patios and shed bases.

%

10% covers spillage and an uneven base.

Job sheet

Concrete calculator
Concrete needed
0.99 m³
0.90 m³ + 10% wastage
In cubic yards
1.29 yd³
25 kg bags (ready-mixed)
87 bags
about 0.0115 m³ a bag
20 kg bags (ready-mixed)
108 bags
about 0.0092 m³ a bag
Ready-mix order
1.00 m³
in steps of 0.25 m³; minimum orders vary
Site mix 1:2:4, cement
13 bags
25 kg bags
Sharp sand
0.70 t
0.44 m³
Gravel (20 mm)
1.31 t
0.87 m³

Estimates only: check your sizes, and the figures on the pack, before you order.

How it works

Concrete is ordered by volume. Measure in metres (100 mm is 0.1 m) and multiply the three sizes, then add a little for wastage.

  • Slab or footing: length × width × depth.
  • Round post holes: π × (diameter ÷ 2)² × depth, less the post, times the number of holes.
  • Steps: width × going × rise × n × (n + 1) ÷ 2, for n steps poured as a solid block.

A worked example

A 3 × 3 m slab, 100 mm thick: 3 × 3 × 0.1 = 0.90 m³. With 10% wastage, that is 0.99 m³ (1.29 yd³).

  • Bags: a 25 kg bag of ready-mixed concrete makes about 0.0115 m³, so 0.99 ÷ 0.0115 = 87 bags (or 108 bags of 20 kg, at about 0.0092 m³ each). Check the yield on your bag.
  • Ready-mix: round up to the supplier’s step: 1.00 m³.
  • Site mix 1:2:4: dry materials take about 54% more room than the concrete they make, so 0.99 × 1.54 = 1.52 m³ of dry mix, split 1 + 2 + 4 = 7 parts: about 13 bags of cement (25 kg), 0.70 t of sharp sand and 1.31 t of gravel.

The weights assume cement at about 1,440 kg/m³, damp sharp sand at 1,600 kg/m³ and gravel at 1,500 kg/m³. These are estimates: for structural work, follow the engineer’s or building control’s specification.

Questions

How many bags of concrete are in a cubic metre?

About 87 bags of 25 kg, or 109 bags of 20 kg, of ready-mixed (dry, just add water) concrete. Brands vary a little: the yield is printed on the bag.

What is a 1:2:4 concrete mix?

One part cement, two parts sharp sand and four parts gravel (20 mm aggregate), measured by volume, with just enough water to make it workable. It is the usual general-purpose mix for bases, paths and footings.

How much extra concrete should I order?

Add 5 to 10% on a slab with formwork, and 10 to 15% for footings dug in soft or uneven ground. Running short halfway through a pour costs far more than a few spare bags.

How do I convert cubic metres to cubic yards?

One cubic metre is 1.308 cubic yards, and one cubic yard is 0.765 cubic metres. The calculator shows both.

Can I order less than a full lorry of ready-mix?

Yes. A full mixer lorry carries about 6 m³, but most suppliers deliver part loads, sold in steps (often 0.25 or 0.5 m³). Small loads often carry a part-load charge: ask when you book.

Got the numbers? Put them straight on a quote.

Price the job on site, add the materials, and your customer signs on your phone. Free for 14 days, no card.

Start free